12 MW solar plant delivered two months ahead of schedule
Project management and supervision of a photovoltaic plant in Alentejo, from licensing to grid connection.
ahead of schedule

Lusenergia had a tight deadline to connect the plant to the grid and secure the contracted tariff. The project involved seven contractors, an environmental licensing process, and imported equipment with uncertain lead times.
We took over project management on the owner's side: weekly integrated plan, cost control per contract, and permanent technical supervision on site. We anticipated the order of inverters and renegotiated the assembly sequence.
- Grid connection two months ahead of schedule
- Budget variance of only 1.8%
- Zero lost-time accidents during construction
- First-year production 4% above the study
Meridiano was our eyes on site. We always knew where we stood and what was coming next.
Other case studies

Pharmaceutical company prepares for European sustainability directive
Decarbonization plan and first sustainability report in accordance with the CSRD directive.

28% more production without new machinery
A metalworking company from Águeda needed to meet more orders without investing in a second line. We reorganized the flow and maintenance with the teams.

Regional bank reduces operational costs by 21%
Efficiency program in back-office operations and the branch network, featuring process automation and a new structure.
Shall we talk about your next challenge?
An initial 45-minute, no-obligation conversation with one of our partners.